The tabular companion to the Field Performance charts, inside settings. Sorted best variance first. Stages read as completed/started so the sample is on screen. An (i) on the heading tells the reader to check the run count before drawing a conclusion. Work with no crew assigned gets its own row rather than being dropped.
Also called: crew on-time rate · which crew is behind · crew days over
- 1Stage logs are grouped by crew; only rows with a variance count toward the averages.
- 2On-time rate = stages with variance at or below zero ÷ completed stages.
- 3Days over sums only the positive variances.
- 4Crews with no stages in the window are filtered out.
The heading's (i): 'Ranked by average variance against baseline. Read the run count first — a crew with two stages behind it is an anecdote, not a trend.' Keeping the unassigned bucket visible matters because unassigned work is itself a scheduling finding.
- Crew comparison required reading the Gantt job by job.
- Unassigned stage work disappeared from every rollup.