A bin-packing pass over every member's cut length. Spliceable members (girts, purlins, eave struts, skirt boards) can be made up from multiple sticks; posts and rafters cannot be spliced and use their own ladder (12/14/16/18/20/24 for treated columns). Each line reports pieces, the stock mix ('12×16′ + 3×20′'), consumed linear feet, purchased linear feet and waste.
Also called: cut optimisation · stock lengths · lumber waste · purchased vs consumed
- 1Cuts are sorted longest-first and dropped into the first bin with room
- 2A cut longer than the yard's longest stock becomes its own special-order piece
- 3Spliced members longer than 20ft explode into 16ft runs plus a remainder
- 4Posts never splice: 'Treated 6x6 columns — yards stock these; never splice a post'
- 5The line carries stock[] (length → qty) and pieces[] (stock, cuts, waste) for downstream use
- 6LVL headers are flagged specialOrder and kept as framed
From the export module's statement of what 'honest' means: 'buy what a yard actually sells (stock lengths), not a 60′ 2x4' and 'show purchase vs consumed vs waste, not a single rounded qty'. A takeoff that reports 480 linear feet of 2x6 is unbuyable; a yard sells sticks.
- Linear feet cannot be ordered — a yard sells pieces at fixed lengths
- Waste is invisible, so the job is under-ordered or over-ordered
See it on your own jobs
Twenty minutes, your numbers, no slide deck. We’ll build one of your real buildings in front of you and send you the estimate link at the end — yours to keep either way.