Days off plan by stage

Average days over or under the planned duration, per stage per crew, drawn around a zero reference line.

What it is

A diverging horizontal bar chart. Left of zero is early, right is late, and the zero rule is drawn — the reference the old chart never had. Bars are coloured by crew to match the legend. The tooltip gives, per crew, the variance, the plan it is measured against, and the sample size: '+1.8d on 5d plan · n=7'.

Also called: variance by stage · which stage runs over · diverging bar chart · over or under plan

See it
Days off plan by stage
Apr
May
Jun
Jul
Ronan Petsch — Riding Arena
Framing
Sutter Kline — 40×64 Shop
Concrete
Ivy Brubaker — 30×40 Garage
Trim
Marlin Hoover — 30×40 Garage
Framing
Delia Yoder — Equipment Storage
Concrete
Framing crewConcrete crewTrim crew
'Days Off Plan, by Stage' — stage names down the left, coloured bars crossing a bold zero line, axis ticks '+2d / -1d'. FieldPerformance.tsx. Sample data — no customer information appears here.
How it works
  1. 1For each stage type present in the current scope, the average variance is computed per crew.
  2. 2The average planned duration and the sample count are carried alongside for the tooltip.
  3. 3A ReferenceLine at x=0 is drawn with a heavier stroke than the grid.
  4. 4Axis ticks are formatted with an explicit sign (+2d / -1d).
Why we built it

A colour decision is documented in the code: 'An earlier pass coloured these by outcome instead and the legend then described nothing on screen — with three bars per stage you could see that something ran late but not which crew ran it, which is the only question the chart is for. Good vs bad is already carried by the axis: left of the zero rule is early, right is late.' And the tooltip: 'The plan and the sample size are what the bar cannot say.'

The problem
  • No drawn reference for 'on plan' meant variance had to be computed mentally.
  • Colouring by outcome made the legend meaningless with multiple crews per stage.
  • The baseline a variance was measured against was not visible.
Sound familiar?
What you get
Over and under are readable by which side of the line the bar falls on.
Crew identity is carried by colour, matching the legend.
Every bar states the plan and the number of runs behind it.

See it on your own jobs

Twenty minutes, your numbers, no slide deck. We’ll build one of your real buildings in front of you and send you the estimate link at the end — yours to keep either way.